Skip to content
Houses on a hillside in Laguna Beach, with palm trees in the foreground

Living here

Building Permits and Design Review in Laguna Beach

Most construction in Laguna Beach needs a building permit, and many exterior projects go through design review first. Community Development runs both, mostly through its online permit portal.

Photo: Beyond My Ken, CC BY-SA 4.0

Department
Community Development, (949) 497-0712
Planning
(949) 497-0713
Building
(949) 497-0715
Permit counter
Monday to Thursday, 7:30 a.m. to 2 p.m.
Design Review Board
Generally the 2nd and 4th Thursday, 5 p.m.

Laguna Beach treats most construction as a two-part process. Planning decides whether a project fits the city’s rules and design standards. The Building Division then checks the structural plans and inspects the work. Both sit in Community Development at City Hall, 505 Forest Avenue.

Do you need a building permit

The city requires a permit to construct, move, alter, convert, improve, repair or demolish a structure, indoors or out. The city’s short list of work that needs none: interior painting, wallpapering, flooring, window coverings and portable plug-in appliances. If your project is not on that list, the city says it probably needs a permit.

A permit applicant is either a contractor licensed in Laguna Beach or an owner who shows proof of ownership and takes on the liability. Building permit fees follow the value of the labor and materials, with separate itemized fees for mechanical, electrical and plumbing work. You pay at your first plan check and again at permit issuance. Community Development posts its fee schedule on its main page, so read the current one rather than a figure from elsewhere.

Rules to know before work starts:

  • Applications filed on or after January 1, 2026 fall under the 2025 Laguna Beach Building Standards Codes.
  • Construction hours are 7:30 a.m. to 6:00 p.m., weekdays only. No work on weekends or federal holidays. Grading runs 8 a.m. to 4 p.m. and hauling 9 a.m. to 3 p.m.
  • Inspection requests must arrive before 4 p.m. for an inspection the next business day. There are no same-day inspections.
  • A permit expires if inspections are not scheduled and passed every 180 days, and every permit needs a passed final inspection.

Small projects and planning review

Minor projects that need no design review may qualify for over-the-counter planning review. The city names re-roofs, fences, air conditioning units and window replacements. It says interior remodels with no exterior change generally skip planning approval and go straight to a building permit application.

Details matter. For roofs, the city generally does not allow white, light tan or light grey colors or highly reflective finishes. Fences and free-standing walls fall under Municipal Code Section 25.50.012, generally between 3 and 6 feet. Chain-link and similar metal fences in residential areas go to design review instead.

When design review applies

Municipal Code Section 25.05.040 lists the improvements subject to design review, and the city says requirements can vary with a property’s earlier approvals. Certain minor classes of work get Administrative Design Review, decided by the Community Development Director or a designee. Everything else goes to the Design Review Board or the Planning Commission.

The rules changed this summer. On July 21, 2026, the City Council adopted the Design Review Efficiency Ordinance. The city lists three changes:

  • Many project types now need a lower level of review. Some new single-family homes may be exempt if they are single-story, no taller than 15 feet and meet other requirements.
  • The review criteria drop from 16 to 11.
  • Administrative Design Review can be approved without a hearing if nobody requests one through the waiver process.

Because the ordinance is new, confirm your project’s level with a planner before you budget time for hearings.

The Design Review Board

The board checks projects against the General Plan, the Local Coastal Program, zoning standards and the design review criteria in the code. The city says it plays a large role in protecting the village atmosphere. Its members are Laguna Beach residents appointed by the City Council to two-year terms.

The board generally meets on the second and fourth Thursday at 5:00 p.m. in the Council Chambers, in person only. To comment on a project, mail or email the board by 3 p.m. the day before the meeting.

How to apply

The city’s own process runs in this order:

  1. Research. Read the zoning code (Title 25), any Specific Plan for your area, the General Plan and the Local Coastal Program. Planners staff a counter at City Hall.
  2. Preliminary zoning review. Register for the Public Permit Portal and submit your plans. There is a fee. A planner returns a letter in about 30 days listing the approvals you need, and the fee covers up to three reviews.
  3. Talk to neighbors. City code requires early neighbor communication on every design review project before the hearing. The board publishes best practices, and city staff offer an optional outreach report form.
  4. File the planning application. The design review application, plus any companions such as a Coastal Development Permit or Variance, is accepted only through the portal. Incomplete applications are not accepted.
  5. Planner review. A status letter arrives in about 30 days. A complete application is tentatively scheduled for a hearing about 45 days later if it qualifies for a CEQA exemption. If the city calls it incomplete, you have six months to respond.
  6. Notice and hearing. The city posts the notice at the site and two other places and mails it to owners within 300 feet and tenants within 100 feet. The code allows three substantive hearings, and the City Council has asked decision-makers to rule within two.
  7. Appeal period. A 14-day appeal and call-for-review period follows. Staking must stay in place, and no building permit application may be filed. Owners within 300 feet can appeal to the City Council. If the project also needs a Coastal Development Permit in an area where that permit is appealable, an appeal to the Coastal Commission can follow within 10 business days of the Commission receiving the city’s notice of final action.
  8. Building permit. Once the decision takes effect, submit construction plans. Design review approvals are valid for two years, and extensions cost a fee.

Planner appointments, by video or phone, are booked through the city’s online portal. The permit counter is open Monday to Thursday, 7:30 a.m. to 2:00 p.m., with the last sign-in at 12:45 p.m. The city warns that a phishing scam targets applicants with pending projects: it never emails requests to wire money, and official email comes from a lagunabeachcity.net address.

Historic Register

The Heritage Committee advises the City Council and the design review bodies on historic preservation, including changes to historic structures. It generally meets on the third Monday at 6:00 p.m.

Listing on the city’s Historic Register is voluntary. The owner must agree, and the property must be on the National or State Register or meet at least one of the city’s criteria, such as heritage value or distinguishing architecture. There is no application fee for placement. After the committee designates a property, the owner signs a preservation agreement recorded with the County that binds later owners. The property is not formally designated until that recording. The city says its older historic inventory no longer creates a presumption that a property is historic.

A Mills Act contract needs Register listing first. The city says it is not accepting Mills Act applications this year while it reviews the program.

Zoning map and GIS lookup

The city’s City Maps and GIS link opens its public GIS map viewer. The viewer’s start screen tells you to search for a property or street and points to its Layers list. Its layers include Zoning, Specific Plan, Land Use, Coastal Area, Historic Parcels (2025) and Fire Hazard Severity Zones. The Planning Division’s Land Use Plans page holds the General Plan, the Local Coastal Program and each specific plan, and the division’s line is (949) 497-0713.

A separate View Restoration Committee, five local residents, hears claims by owners that vegetation blocks a view. If a project involves moving in, the moving checklist covers meter bags and permits for the street. The city services directory lists other department numbers.

Before a sale, the city also requires a Real Property Report on the property.

Questions

Do you need a permit to remodel in Laguna Beach?

Usually, yes. The city lists interior painting, wallpapering, flooring, window coverings and portable plug-in appliances as work that needs no permit, and says a project not on that list probably does.

How do you apply for a building permit in Laguna Beach?

Register for the city's Public Permit Portal, then submit your plans and application there. The Building Division answers questions at (949) 497-0715.

When does a project need Design Review Board approval?

It depends on the project. Municipal Code Section 25.05.040 lists what is subject to design review, certain minor classes get Administrative Design Review, and the rest go to the Design Review Board or Planning Commission. A July 2026 ordinance changed which projects need which level, so ask a planner.

When does the Laguna Beach Design Review Board meet?

The city says it generally meets on the second and fourth Thursday of each month at 5:00 p.m. in the Council Chambers, in person only.

How does a house get on the Laguna Beach Historic Register?

The owner files a Historic Register Placement Application, and the Heritage Committee reviews it. The owner must agree to the listing and sign a preservation agreement recorded with the County, and the city charges no application fee for placement.

Get the moving checklist

The printable checklist by email: before you move, moving week and your first 30 days.

Or call (949) 494-8830. Your details go only to our real estate sponsor, Realatrends Real Estate (DRE #00925482); see our privacy notice.

Living here

More for your move

All of Living here

Last reviewed

Sources (13)
  1. Building permits and zoning plan checks go through the Public Permit Portal (register an account, then submit plans and application); building permit required for constructing, moving, altering, converting, improving, repairing or demolishing a structure, inside or out; licensed contractor or owner proof of ownership; fees based on valuation with separate itemized mechanical, electrical and plumbing fees, paid at first plan check and permit issuance; 2025 Laguna Beach Building Standards Codes apply to applications on or after January 1, 2026; construction hours 7:30 a.m. to 6:00 p.m. weekdays only, none on weekends or federal holidays; grading 8 a.m. to 4 p.m.; hauling 9 a.m. to 3 p.m.; inspection requests before 4 p.m. for the next business day, no same-day inspections; permits expire if inspections are not scheduled and passed every 180 days; final inspection required; Building Division (949) 497-0715; permit records searchable on the portal: lagunabeachcity.net, checked 2026-10-28
  2. Permits required before constructing, enlarging, altering, repairing, moving, demolishing or changing a building or an electrical, mechanical or plumbing system; projects that do not need a permit: interior painting, wallpapering, flooring, window coverings, portable cord-and-plug appliances; if a project is not on the list it probably needs a permit: lagunabeachcity.net, checked 2026-10-28
  3. Community Development contacts: department (949) 497-0712, Planning (949) 497-0713, Building (949) 497-0715, Code Enforcement (949) 497-0301; permit counter Monday to Thursday 7:30 a.m. to 2:00 p.m., last sign-in 12:45 p.m.; appointments with a planner or plan reviewer; the city will never email asking you to wire money and official email comes from lagunabeachcity.net addresses; a department fee schedule is posted: lagunabeachcity.net, checked 2026-10-28
  4. Design review process: research ordinances, Specific Plans, General Plan and Local Coastal Program; preliminary zoning review through the portal with a fee, a Zoning Plan Check number, a letter in about 30 days and up to three reviews on the fee; early neighbor communication required for all design review projects before a hearing (LBMC 25.05.040(C)(1)); planning applications for design review and companion applications such as a Coastal Development Permit, Variance and Revocable Encroachment Permit accepted only through the portal; status letter in about 30 days; complete applications tentatively scheduled for a public hearing about 45 days later if exempt from CEQA; six months to answer an incomplete letter; hearing notice posted at the site and two other places, mailed to owners within 300 feet and tenants within 100 feet; Administrative Design Review by the Community Development Director or designee, Design Review Board and Planning Commission twice a month in Council Chambers; code limits to three substantive hearings and two non-substantive continuances, and the City Council has directed decisions within two hearings; 14-day appeal and call for review period with staking kept in place and no building permit application filed; owners within 300 feet may appeal to the City Council, hearing within 60 days; where a Coastal Development Permit is also needed, many projects are in areas where that approval may be appealed to the Coastal Commission, and an aggrieved party or the Commission may appeal within 10 business days of the Commission's receipt of the city's Notice of Final Action; the Design Review Board prepared best practices for neighbor outreach and staff prepared an optional Neighborhood Outreach Report; design review approvals valid for two years, extensions for a fee: lagunabeachcity.net, checked 2026-10-28
  5. On July 21, 2026 the City Council adopted the Design Review Efficiency Ordinance (Urgency Ordinance No. 1732): many project types now need a lower level of review; certain new single-family homes may be exempt if single-story, no taller than 15 feet and meeting other requirements; design review criteria cut from 16 to 11; hearing waiver option for Administrative Design Review: lagunabeachcity.net, checked 2026-10-28
  6. Design review is described in Municipal Code Section 25.05.040 and varies with a property's prior entitlement history; certain minor classes get Administrative Design Review and all others go to the Design Review Board or Planning Commission; minor projects such as re-roofs, fences, air conditioning units and window replacements may be reviewed over the counter; interior remodels with no exterior changes generally skip planning approval; re-roof colors: the city generally does not allow white, light tan or light grey or highly reflective finishes; fences generally 3 to 6 feet and chain link in residential areas goes to design review; planning review turnaround about 30 days: lagunabeachcity.net, checked 2026-10-28
  7. Design Review Board assesses projects against the General Plan, Certified Local Coastal Program, zoning standards and the design review criteria in Municipal Code 25.05.040(H); members serve two-year terms; generally meets the second and fourth Thursday at 5:00 p.m. in person in the Council Chambers; written comments by mail or email to the board no later than 3 p.m. the day before; members and Planning Commissioners are Laguna Beach residents appointed by the City Council: lagunabeachcity.net, checked 2026-10-28
  8. Heritage Committee advises the City Council and design review authority on alterations to historic structures, Historic Register requests and Mills Act recommendations; two-year terms; generally meets the third Monday at 6:00 p.m. in the Council Chambers: lagunabeachcity.net, checked 2026-10-28
  9. Historic Register: voluntary listing; owner must agree and meet one or more criteria or be on the National or State Register; no application fee; a preservation agreement is recorded with the County and applies to later owners, and a property is not formally designated until it is executed and recorded; Mills Act applications not accepted this year while the city reviews the program; the prior inventory under Ordinance No. 82.111 does not create a presumption of historicity: lagunabeachcity.net, checked 2026-10-28
  10. View Restoration Committee of five residents hears view claims from property owners about vegetation: lagunabeachcity.net, checked 2026-10-28
  11. City Maps and GIS (linked from the city's Find menu and Do Business Here pages) opens the public GIS viewer at gis.lagunabeachcity.net/Html5Viewer/index.html?viewer=LagunaBeachPublicGIS: lagunabeachcity.net, checked 2026-10-28
  12. Laguna Beach Public GIS Map Viewer: start screen instructions say search for a property or street and access measurements, tools and the Layer list; layers include Zoning, Specific Plan, Land Use, Coastal Area, Historic Parcels (2025), Fire Hazard Severity Zones and Parcel (opened in the in-app browser): gis.lagunabeachcity.net, checked 2026-10-28
  13. Planning Division Land Use Plans page: General Plan, Local Coastal Program and specific plans (Arch Beach Heights, Diamond-Crestview, Downtown, Laguna Canyon Annexation Area, Sarah Thurston Park, Treasure Island); Planning Division (949) 497-0713: lagunabeachcity.net, checked 2026-10-28